Omar Nabeel

Team Leader – Major Bridges & Technical Director, Rendel

Omar Nabeel, MEng CEng MICE, Major Bridges Team Leader & Technical Director has over 13 years of experience through all stages of the design and construction process of major infrastructure projects both in the UK, and internationally.

This includes feasibility studies, reference design, tender design, detailed design, independent checking, erection engineering, and construction supervision. Omar led the global analysis and erection engineering for the 3.4km long Colne Valley Viaduct as part of Phase 1 of HS2.

This precast segmental, post-tensioned, box girder structure with spans up to 80m will be the longest railway viaduct in the UK when complete. Other major projects Omar has been involved include Wadi Laban in Saudi Arabia; Howrah Bridge in India; Sydney, Australia, Metro Northwest; and the Garden Bridge UK.

My Speaker Sessions

Wednesday 12 March 2025

14:20

Modern Methods of Construction - The Colne Valley Viaduct being delivered by the Align JV as part of HS2 Phase One in the UK

14:20 - 14:40
  • When completed, the 3.4km-long Colne Valley Viaduct (CVV) constructed as part of Phase 1 of High Speed 2 (HS2) will be the longest railway viaduct in the UK.
  • This precast, segmental, post-tensioned concrete box girder viaduct has been erected by an overhead gantry – the only one of its kind currently being employed in the UK.
  • This 650t gantry has been used to erect the segments of the viaduct through both balanced cantilever and span-by-span methods.
  • This method of erection and choice of erection equipment has enabled the viaduct to be constructed entirely above pier head level, with segments rear fed to the gantry at deck level, delivered by trailer on the previously erected spans.
  • This has minimised disruption both on the surrounding roads and the highly environmentally sensitive bodies of water and woodland areas, northwest of London, which the viaduct spans.